Project: Wind Turbine
Project Description
Myshak Crane & Rigging was requested to build 9 towers in 2 months time in southern Alberta. The challenge was the height of turbines being built and the weight of the wind turbine itself. Lots of hills and wind speeds from 0-25mph made for a tough time to assemble the crane and an even shorter timeframe to lift the turbines into place. After the first two turbines we had to move the crane 4 times to complete the remainder of lifts.
What We Did
Services included in this project were Trucking to deliver crane parts took 13 loads with boom, counterweight and all rigging.
Details
Date Completed:August 27, 2016
Equipment Used:
- MTG - Transportation
- 5 - Trucks & Trailers
- MCR - Cranes
- 1 - 440Ton Liebherr LR1400-2
- 1 - 160Ton Liebherr LTM 1130/5.2
- MSR- Service Truck, Zoom boom
- 1 - 100Ton Tadano GR 1000XL
- Crane MATS
- Rigging (Bars, Slings, Shackles, Man basket)